Liverpool City Council is one of the fastest-growing Local Government Areas (LGAs) in New South Wales. Over the next ten years, Liverpool will continue to experience significant growth and transformation across economic development, population, housing and infrastructure delivery, including the provision of social infrastructure to support the needs of a growing community.
Council has adopted a range of long-term strategies to guide the future planning and delivery of community facilities, recreation spaces, open space and sports infrastructure across Liverpool. These strategies help ensure community needs remain at the forefront of planning and decision-making, while addressing current and future demand for high-quality recreational and social infrastructure.
Council is currently progressing the planning, design and delivery of open space projects across Austral to support the needs of the growing community. The Austral Open Space Delivery Map provides an overview of the current status of parks, recreational spaces and associated projects across the precinct.
Council is also progressing planning for recently acquired open space lands to support the delivery of accessible parks and recreation opportunities for the community.
Detailed information on the status of individual open space projects, including concept designs, masterplans and delivery stages, can be found below. These projects will help guide short- and long-term delivery priorities through Developer Contribution Plans, Council’s Delivery Program, and future grant and funding opportunities.
To view and download a high-resolution version of the Austral Open Spaces Planning and Delivery map, please follow the link:
Austral Open Spaces Planning and Delivery Map

What is the current status?

About
Liverpool City Council is pleased to advise that planning for the development of Local Park 2, located at 335 Sixth Avenue, Austral, is progressing.
The project aims to deliver new recreational facilities for the enjoyment of the local community. The proposed works include a children's playground with a softfall rubber surface, an outdoor fitness gym, concrete footpath connections, new park furniture and landscape enhancements.
Community consultation for the Draft Concept Plan closed on 26 April 2026. Following consideration of community feedback, the Concept Plan has now been finalised and is available to view on Liverpool Listens Concept Plan - Local Park 2 in Austral | Liverpool Listens.
The design consultant has commenced preparation of the detailed design documentation for the remaining works. Community members who participated in the consultation were notified of the final Concept Plan.
Image 1: Austral Local Park 2 Birdseye View for final design documentation.

Image 2: Austral Local Park 2 View for final design documentation.
Next Steps
The Project will be completed in design stages as per below:
Stage 1 – Construction of the local playground has been completed, and the playground was officially opened on 11 July 2026.
Stage 2 – Detailed Design of open lawn with flexible use, an outdoor fitness gym, concrete footpath connections, installation of new park furniture and landscape enhancements scheduled to commence in financial year 2026-2027.
Note: The commencement of design and delivery for all projects is subject to budget approval.
What is the current status?
About

Image 1: Austral Local Park 6 Concept Plan.
Council has created a concept design for the future development of ‘Local Park 6’ in Austral, located between Tenth Avenue, Horologium Road, Aries Street, and Magellanic Street. The concept design is based on community feedback around open-space needs across Austral, and delivers on Council’s Recreation, Open Space and Sports Strategy.
Key features include:
- Playground space with play equipment and rubber soft fall
- Shade structure
- Picnic shelter with tables and seats
- Nature play area with timber logs and steppers
- Ping pong table
- Planting and trees

Image 2: Austral Local Park 6 Artist Impression – active play area.

Image 3: Austral Local Park 6 Artist Impression – nature play area.
Community Consultation
Council undertook community consultation to seek feedback on the proposed concept design prior to progressing the project to the delivery stage. The concept design document included a site plan outlining the proposed layout and key design features, supported by visual renders to assist the community in understanding the proposed park design.
The consultation period ran from 2 February 2026 to 2 March 2026. Community members were invited to provide feedback through three main channels:
- Liverpool Listens online survey
- Written feedback via email or post
- Engagement with Council staff at a community event
Overall, 51.49% of respondents indicated that they liked the proposed design, while 27.61% did not like the design and 20.90% were unsure.

Positive feedback – What the community liked | Areas for improvement – What the community wanted more of |
|---|---|
63.43% preferred the play space with play equipment and soft rubber fall. | Feedback indicated a desire for a park that caters for a broad range of ages and abilities. |
55.97% preferred the shade structure. | Residents wanted a better balance between open space and active recreational uses. |
40.30% preferred the nature play area. | Residents expressed a desire for additional facilities supporting play, fitness and social interaction. |
The consultation also indicated that the proposed park is expected to be used primarily on a daily basis, particularly during the evening period between 5 pm and 9 pm.

Overall, the consultation feedback demonstrates a strong desire for a larger, more inclusive and engaging park that responds to the needs of the rapidly growing, family-oriented community.
Council will consider the feedback received through the community consultation process when refining the park design during the detailed design stage, subject to the availability of funding, site constraints and relevant technical requirements.
Next Steps
Detailed Design - is scheduled to commence in financial year 2026-2027.
Note: Please note, timing for the delivery of the park will be subject to funding availability and allocation. Works may be staged to accommodate funding availability
What is the current status?
About
Council has created a concept design for the future development of ‘District Park 11’ in Austral, located between Gurner Avenue and Swamphen Street. The concept design is based on community feedback around open-space needs across Austral, and delivers on Council’s Recreation, Open Space and Sports Strategy.
Key features include:
- Inclusive shaded play space
- Open lawn area for play and socialising
- Picnic shelter with tables and seats
- Fun, playful embankment features (pavers and timber logs)
- Planting and trees

Image 1: District Park 11 Concept Plan.

Image 2: District Park 11 Artist Impression – active play area.

Image 3: District Park 11 Artist Impression – embankment nature play area.
Conmmunity Consultation
Council undertook consultation to seek community feedback on the proposed concept design prior to progressing to the delivery stage.
The consultation period ran from 2 February 2026 to 2 March 2026. Community members were invited to provide feedback through three main channels:
- Liverpool Listens online survey
- Written feedback via email or post
- Engagement with Council staff at a community event
Overall, 59.3% of respondents indicated that they liked the proposed design, while 27.91% did not like the design and 12.79% were unsure.

Positive feedback – What the community liked | Areas for improvement – What the community wanted more of |
|---|---|
55.81% preferred the play space with play equipment and soft rubber fall. | Residents wanted greater scale, variety and overall provision. |
53.49% preferred the picnic setting. | Residents wanted more facilities and activities for older children, teenagers and adults. |
52.33% preferred shade structure. | Feedback highlighted the need for adequate infrastructure and capacity to meet future demand. |
The survey indicates the proposed park will be mostly used daily and in the evenings between 5pm and 9pm.
The community strongly supports the delivery of District Park 11 and views it as critical infrastructure for Austral. However, there is a clear and consistent message that more facilities are desired to meet the needs of the local population.
Council will consider the feedback received through the community consultation process when refining the park design during the detailed design stage, subject to the availability of funding, site constraints and relevant technical requirements.
Next Steps
Detailed Design - Scheduled to commence in financial year 2026-2027.
Note: Please note, timing for the delivery of the park will be subject to funding availability and allocation. Works may be staged to accommodate funding availability.
What is the current status?

About
Local Park 22 is located adjacent to Austral Public School at the corner of Tenth Avenue and Biffin Lane, Austral. The park is being delivered on Council-owned land and is co-located with the existing Austral Neighbourhood Centre and the future community centre.

Image 1: Local Park 22 Stage 01 Playground - complete and open to public. Liverpool City Council July 2026.
The park has been designed to provide a welcoming recreational space for the growing community, offering opportunities to connect, play and enjoy the outdoors while enhancing the surrounding landscape.
Image 2: Local Park 22 Concept Design Plan.
Council has approved the concept design following community consultation and feedback from local residents, the school community and other stakeholders. The scope of works has since been refined and divided into two delivery stages to align with the available budget allocation and funding.
Next Steps
The Project will be completed in design stages as per below:
The project will be delivered in the following stages:
Stage 1 – Construction of the inclusive playground has been completed, and the playground was officially opened on 3 July 2026.
Stage 2 - Detailed Design of an outdoor fitness gym, concrete footpath connections, installation of new park furniture and landscape enhancements scheduled to commence in financial year 2026-2027
Note: Delivery of Stage 2 works is subject to budget allocation and funding.
What is the current status?
About
Craik Park is an established park located at the corner of Eleventh Avenue and Fourth Avenue. It is currently home to the Western Blue Athletics and the Austral City Bears. Due to its proximity to St. Anthony of Padua Catholic College, this park is visited by a large amount of our younger residents.
Craik Park was previously an old showground but now functions as a local sportsground. Located just 10 kilometres southeast of the Western Sydney Airport and in close proximity to the Western Sydney Aerotropolis, it holds significant potential for its future as a local town park, meeting the many day-to-day passive and active recreation needs of its community.
Image 1: Craik Park Context Map.
Council has endorsed the final masterplan on Dec 2024 to establish the improvements and facilities required to meet its rapidly growing community. Council also adopted the draft Plan of Management and planning to send to Crown Land for approval for public exhibition. Further information will be updated in the future.
The upgrade to Craik Park is a proactive response to the population growth in Liverpool and the lack of recreation and open spaces in Austral. The first steps to achieving this is the upgrades to the existing playground to meet the immediate recreational needs of the community. Below are the final Master Plans that have been produced thus far.
The Contributions Plan for Craik Park notes that the masterplan should accommodate demand for local sport and recreation training and competition.

Image 2: Craik Park master plan vision and objectives.

Image 3: Craik Park master plan concept.
Next steps
Detailed Design of Stage 1 (upgrades of the sports oval, fencing, flood lighting, amenities building, car park and pathways) – Scheduled to commence in financial year 2026-2027.
Note: The commencement of design and delivery for all projects is subject to budget approval.
What is the current status?
Where is the project taking place?
WV Scott Memorial Park is an established park located at the corner of Edmondson Avenue and Bringelly Road. It is currently home to the Austral SC and the Fairfield Liverpool Cricket Association.
The park is classified as a Local Passive Open Space. The Austral North and Leppington Contributions Plan notes that local parks should have a range of play spaces and opportunities and cater to older children and young people as well as the traditional playground for young children.
About
Image 1: WV Scott Memorial Park Draft Leppington ILP 2022.
WV Scott Memorial Park is an established park located at the corner of Edmondson Avenue and Bringelly Road. It is currently home to the Austral SC and the Fairfield Liverpool Cricket Association.
The park is classified as a Local Passive Open Space. The Austral North and Leppington Contributions Plan notes that local parks should have a range of play spaces and opportunities and cater to older children and young people as well as the traditional playground for young children.
Council is planning two-staged master plan implementation to support existing and future community.
The short-term outcomes of this project are:
- To improve the capacity and accessibility of the existing park, taking in consideration that Scott Memorial Park is the designated location of the future regional Austral Aquatic and Leisure Centre (AALC).
- Re-using existing floorspace to cater for some of the longer-term needs must be considered.
- To upgrade the existing children’s playground to suit all ages and the existing sport courts to multi-sport games court.
- For toilet facilities to be of public access.
- To redesign the existing car park to incorporate accessible parking and additional spaces if needed.
- To improve/incorporate walking and biking trails and to consider connectivity to surrounding open spaces and green corridors.
- To improve changerooms and spaces for the current Austral Soccer Club to cater for short term growth.
The plan also includes temporary assets to increase the capacity of the existing sports clubs and the addition of a multi-sport court.
Image 2: VW Scott Memorial Park short term master plan.
The long-term master plans include:
- Aquatic facilities include an indoor 50 metre x 10 lane Olympic pool, training pool, 25 metre leisure pool, heated teaching pool; children’s play pool / wave pool / whirl pool/ water slides, diving pool.
- Indoor Sports to include 4 indoor sports courts each large enough for netball.
- Fitness centre incorporating weights, aerobics/Dance/Yoga/Pilates activity room with wooden floor, spin cycle room,
- Wellness / health services – physiotherapy, nutrition etc
- Spa, sauna, steam room
- Retractable seating for 1,500 this would increase to 3,500 in stage 2.
- General amenity, kiosk and café, equipment sales, change, lockers, toilets, crèche facilities for users
- Outdoor elements - may include water play park, BMX, skate, sports oval and netball, tennis, basketball courts. May be integrated with a youth recreation facility.
Image 3: VW Scott Memorial Park long term master plan.
Next Steps
Construction of Inclusive playground Stage 1 – Scheduled to commence in year 2026.
Construction of floodlights upgrades of dual soccer field – Scheduled to commence in year 2026.
Note: The commencement of design and delivery for all projects is subject to budget approval.