Many of Council's facilities, including the Customer Service Centre, are closed to the public until further notice.

Click here for information about changes to Council's services and facilities.

Current Major Works

Cirillo Sporting Facility

Cirillo Reserve, Middleton Grange

Budget: $8.2 million
Start date: November 2019
Finish date: November 2020

Work has started on two new sports fields, cricket pitch, floodlighting, sports amenities building, playground, outdoor fitness gym and an off-leash dog park.


Fifteenth Avenue upgrade

Fifteenth Avenue Upgrade

Fifteenth Avenue, Cowpasture Road to Devonshire Road

Budget: $1.5 million (Design phase only)
Start date: October 2019
Finish date: January 2022

Design work on proposed Rapid Transit Corridor between Liverpool CBD and Western Sydney International Airport. A consultant has been selected for strategic concept design, which will start in October 2019. Final detailed design expected in January 2022.


Phillips Park

Lurnea Community Hub

Phillips Park, Hill Road, Lurnea

Budget: $16 million
Start date: March 2020
Finish date: March 2021

Work about to begin on a new multi-purpose community hub, dual soccer/cricket sports oval, improvement to pathway network, car parking, children’s playground, outdoor fitness gyms, lighting and picnic facilities.


Edmondson Avenue upgrade

Edmondson Avenue Upgrade

Edmondson Avenue, Bringelly Road to Fifteenth Avenue

Budget: $1.6 million (Design phase only)
Start date: July 2018
Finish date: June 2020

Design only. Stage 1 – Bringelly Road to Seventh Avenue. Stage 2 – Seventh Avenue to Fifteenth Avenue. Concept design and traffic modelling is complete. Awaiting information from Transport for NSW on traffic signal locations.


Lighthorse park

Lighthorse Park Upgrade

Liverpool

Budget: $500,000 (Design only)
Start date: August 2020
Finish date: January 2021

Tender being prepared for design of Lighthorse Park upgrade including sports fields, community centre, playgrounds and gardens.


Stante Reserve

Stante Reserve, Middleton Reserve

Budget: $2 million
Start date: May 2020
Finish date: Oct 2020

Construction of water play park, playground, amenities building and landscaping.


McGirr Park Tennis Courts

McGirr Park, Miller

Budget: $1.3 million
Start date: Dec 2019
Finish date: Aug 2020

Work under way on four tennis courts – two synthetic grass and two hard flexi pave – with fencing, floodlights and amenities building.


Georges River Boardwalk and Crossing

Georges River Boardwalk and Crossing

Liverpool

Budget: $500,000 (Design phase only)
Start date: April 2016
Finish date:
Dec 2020

Design work under way for a pedestrian bridge built on the existing heritage-listed railway pylons. Tender has been advertised for design of a vertical connection between Liverpool train station and Lighthorse Park.


 Middleton Drive Extension

Middleton Drive Extension

Middleton Drive, Middleton Grange

Budget: $350,000 (Design phase only)
Start date: Sept 2017
Finish date: June 2021

The project involves construction of a missing road link under the M7 Motorway, linking Aviation Avenue and Middleton Drive. This year’s budget includes funding for detailed design of grade separation of the M7 cycleway at Middleton Grange and detailed design of missing link between Middleton Road and Aviation Road.


Speed Street Car Park

Speed Street, Liverpool

Budget: $450,000
Start date: December 2019
Finish date: June 2020

Work under way on construction of car park with 77 spaces.